Construction work for reconstruction of Quays 18, 22 and 23 of the Admiralty Basin in the Old City Harbour

Period: 9.2014 – 6.2012
Customer: AS Tallinna Sadam
Description of work: New steel sheeting anchored with injection anchors in front of the wooden poles of the existing quay. Reinforced concrete edge beam, concrete stone pavement, water supply, storm water drainage, power and communication installation. Total length of quays: 450m.